Delarch House, Webber Row, Southwark

Print this page Click here to tip a friend about this page!

Supporting beams across the landing level on the stairwell at Delarch House, needed repairing and strengthening.

Once repaired the corner of the beams were rounded off to enable 100% bond of the carbon fibre.


The beams were inspected and cut back to sound concrete, then repaired using weber.cem keycoat and weber.cem HB mortars.

Weber attended site to instruct and demonstrate application of the Enforce composite strengthening system. One layer of weber.tec force carbon sheet C240 was applied the full length of the beam, each sheet overlapping 100mm. The beams were then blinded with sand in preparation for decoration planned in phase two of the works.